1. pl
  2. en

Methodology - SCRUM
 

Communication:

2-week sprints

  • Daily

  • Planning 

  • Backlog refinement 

  • Sprint Review 

  • Sprint Retro 

 

Other meetings

  • Client meetings once a week

  • Official reports every 2 weeks 

Project NGS - preparation of devices for their integration into a chain of interconnected devices cooperating with each other in cloud technology.

QIASymphony SP performs fully automated nucleic acid isolation using magnetic particle technology. This device is equipped with various protocols and control sets for tests used to purify RNA, DNA, as well as viral and bacterial nucleic acids.

Responsibility:

  • Managing a technical team consisting of programmers and QA specialists.
  • Managing the backlog, sprint execution, planning, and reporting.
  • Coordinating actions between departments, including quality control, service, and procurement.
  • Supervising documentation and change control procedures in accordance with medical regulations (FDA).

TEAM:

  • 2 developers (no frontend, no backend)
  • 2 testers (only manual testing)

  • Project manager (responsible for the project)

  • Line manager (responsible for resources, motivation, support, recruitment)
     

Tools :  Jira, MS Teams, MS Project, Confluence

Methodology - SCRUM
 

Communication:

2-week sprints

  • Daily

  • Planning 

  • Backlog refinement 

  • Sprint Review 

  • Sprint Retrospective 

 

Other meetings

  • Client meetings once a week

  • Official reports once every 2 weeks 

Project RGAM

The QIAGEN real-time PCR cycler, Rotor-Gene Q, combines many optimized design elements to ensure excellent performance and reliable results that your research requires. Combined with optimized QIAGEN real-time PCR kits, the Rotor-Gene Q enables streamlined analysis for a wide range of applications.

PROJECT - Adaptation of RGAM 2.1 to the new Windows 10 operating system. Along with this change, several so-called off-the-shelf software components (e.g., Microsoft SQL Server) will be updated to ensure that the entire application package is compatible with the new operating system.

RGAM TEAM 3 manual testers

  • 1 automation tester

  • 2 developers

  • Project manager

  • Line manager
     

Tools: Jira, Excel, MS Teams, MS Project, Confluence.

Logo Primer support company